Summary
A sewer main on Burr Oak Boulevard failed during last August's floods. An emergency repair was completed, and the board has now awarded a contract to line and reinforce the rest of that section so it doesn't fail again.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 21, 2026.
Impact analysis
The $398,821 contract is over budget, but savings from other already-bid projects will cover the difference — no new money from taxpayers.
Residents in the Burr Oak area get a more reliable sewer main less likely to back up in heavy rain.