Clean Water Plant sand filter defects
The city's wastewater plant scored a perfect 4.0 on its state compliance report for the tenth year running, even weathering a 200-year rain event. A sludge dryer project will turn plant solids into a DNR-approved Class A biosolid product the public could eventually purchase.
Deer Path flood mitigation timing
Residents of the Deer Path subdivision begged the committee to speed up flood mitigation construction from 2028 to 2027, describing repeated basement flooding and boat rescues. Staff say design, utility coordination and grant timing make 2028 realistic.
Patrick Ponds and Summit Woods Pond Rehabilitation
The city is spending about $2.5 million to rehabilitate two neighborhood stormwater ponds, keeping drainage working and reducing flood risk. The low bid from C.W. Purpero, Inc. was recommended for award.
Pump stations improvement project
The city awarded a $2.08 million contract to Mid City Corporation to replace the Ruben Drive sanitary pump station — key sewer infrastructure for that neighborhood.
Backyard main letters — Hine, Glenn, Cumberland and Summit
Dozens of homes have water mains running through their backyards without proper easements, and the city attorney's office says the utility must fix it — moving mains, reconnecting services, and making homeowners whole. Expect letters to residents, years of phased construction, and costs borne by ratepayers.
Burr Oak Boulevard sewer repair and lining